| Task | Date | Status | Remark |
| Project Website Setup | Original website down, rebuilding a new one. Plan to complete recovery on 10/28/04 | ||
| GODS 1.0 Alpha Release | 11/02/04 | ||
| SourceForge Setup | 11/04/04 | ||
| Class presentation I | 11/04/04 | ||
| GODS 1.0 Beta Release | 11/09/04 | Rescheduled from 11/04/04 | |
| GODS 1.1 Requir. Meeting I | 11/18/04 | Also for client to critique GODS 1.0 | |
| ERS Draft | 12/02/04 | ||
| GODS 1.0 Release | 12/03/04 | Rescheduled from 11/16/04 Rescheduled from 11/09/04 |
|
| GODS 1.1 Requir. Meeting II | 12/07/04 | Also
for client to critique GODS 1.0 Rescheduled from 11/30/04 |
|
| Class presentation II | 12/14/04 | Rescheduled from 12/09/04 | |
| ERS | 12/16/04 | ||
| Mail merge client install/test I | 02/05/05 | ||
| Mail merge client install/test II | 02/17/05 | This completion date depends on client's schedule | |
| Database Remodel w. 1.0 spec | 03/02/05 | Rescheduled to 03/15/05 for reflecting 2.0 spec | |
| Database Remodel w. 2.0 spec | 03/15/05 | Rescheduled from 03/02/05 | |
| Screen Capture Module, Browse and Search Module, MarkSet Config Module, Main Workspace Module | 03/22/05 | All modules execpt MarkSet Config module, And team decide to have MarkSet config absolutely isolated so that it won't affect the Integration process. | |
| Modules integration, Regression test on 1.0 spec, test on 2.0 spec without teaching library | 03/24/05 | Integration is done except the mark config part. test are performed and some bugs are fixed. Team will set up the bug tracking system. | |
| Full working version (no teaching library) without knowing bugs | 03/31/05 | Prepare for GODS 2.0 Alpha Release | |
| GODS 2.0 Alpha Client Meeting for feedback | 04/05/05 | The client meeting is set on April 7th. | |
| GODS 2.0 Alpha | 04/24/05 | Modified Alpha version based on feedback | |
| Department Presentation | 05/04/05 | GODS2.0 Beta version presentation | |
| GODS 2.0 Beta Release | 05/13/05 | GODS2.0 with mailmerge functionality integrated |